Notice: Cherry Street Closure

Construction of the new Downtown Transit Center has begun.  The LINK buses have been relocated from St. Paul Street to the north and south sides of Pearl Street as the first step in that process.

The next steps will involve the installation and relocation of utilities at the intersection of Cherry and St. Paul Streets.  The installation of a new sewer line will take place over the weekend of July 17, 18, and 19th.  Construction will begin on Friday evening ad will continue around the clock until early Monday morning.  During that time, Cherry Street will be closed to vehicular traffic between South Winooski Avenue and Pine Street.  Pedestrian access will be maintained throughout the weekend.  Vehicular access will be maintained to the Mall parking garage on Cherry Street and the parking garage adjacent to Macy’s.  Pine Street will remain open to traffic; however, St. Paul Street will have very limited access.

CCTA appreciates your understanding and cooperation as they work to create a first class Transit Center for downtown Burlington.