As part of the Great Streets Project, Construction continues on Saint Paul Street. Below is a summary of what has been completed in the last week and what in the works for the week ahead.
NOTE: Parking is FREE for the first hour at 194 St Paul Street covered lot ($1/hr thereafter), businesses will remain open throughout construction and pedestrians are always welcome. See map below for more info or check out our interactive map for other parking options.
What Happened Onsite Last Week
SD Ireland continued excavating for subbase and placing subbase between Maple Street and King Street and the East side of the Maple Street intersection. Grading began on the King Street intersection and between King Street and Maple Street. Crews began removing sidewalk on the west side between the Hilton/TD Bank exit and Main Street, they installed sidewalk subbase in this location as well.
Next Week Look Ahead
SD Ireland will be fine grading the new subbase in the Maple Street intersection and between King Street and Maple Street. Paving of the Maple Street intersection and between King Street and Maple Street will be completed on Tuesday and Wednesday. SD Ireland will continue working on removing existing sidewalk and excavating and placing subbase for under the new sidewalk on the west side of the block between Main Street and King Street. Once the west side is complete the crew will move to the east sidewalk area.
Possible impacts
King Street and Maple Street will have flagged traffic while fine grading and paving. Hilton/TD Bank exit will change to outlet onto Main Street early in the week. The west sidewalk between King Street and Main Street will be closed to through pedestrian traffic, once sidewalk subbase is installed it will be re opened and the east sidewalk will be closed to through pedestrian traffic. The cross walk on the south side of Main Street will be closed to pedestrians for the week.
Contact
For questions related to activity on-site, please contact Katelyn Dagesse, our engineer on-site from EIV, at 802-673-0001.
For questions related to the overall project, please contact Robert Goulding, DPW Public Information Manager, at [email protected] or 802-540-0846.
Thank you for your patience in this process.